Join Christopher Villari, Communications Manager, as he walks through the LaGuardia Airport (LGA), Terminal B Redevelopment project.

 

Chris manages and coordinates stakeholder interaction, internal and public communications and corporate community investment initiatives for the LGA project. He and the LGA team have been working on the project since 2016, with a phased completion scheduled for 2022. The videos below highlight critical aspects of the project.

Project at a Glance

Client

LaGuardia Gateway Partners LLC

 

Architect

WSP/HOK - New York

 

Construction Cost

$4,006,000,000


Size

1,300,000 SF

 

Delivery Method

Design-Build, P3/Design-

Build-Finance-Operate-

Maintain (DBFOM)

 

Completion Date

June 2022

 

LEED® Certification

LEED Gold and

Envision Platinum

 

 

Project Overview

Latest Update

West Parking Garage (Updated Dec 2018)

Headhouse-Western Rooftop (Updated Dec 2018)

Headhouse-Eastern Rooftop (Updated Dec 2018)

Temporary Platform (Updated Dec 2018)

Headhouse: Food and Beverage/Retail (Updated Dec 2018)

Headhouse: Main Departure Hall/Ticketing (Updated Dec 2018)

Baggage Handling System (Updated Dec 2018)

Terminal B (under construction) - (Filmed May 2018)

For more information about the LaGuardia Airport (LGA), Terminal B Redevelopment project you can reach out to:

Emily Toliver

Marketing Manager

Aviation COE

Emily.Toliver@skanska.com

Dwight Pullen

Senior Vice President

Aviation COE

Dwight.Pullen@skanska.com